The driving range project has gotten off to a slow start this week due to it raining four out of five of the days so far. The Golf Club has not been able to export dirt due their site being too wet, but the delay has actually worked out in our favor allowing us to complete several necessary details.
Our biggest obstacle was getting final approval from the County, which occurred yesterday. In order for us to begin taking dirt on our site, we had to meet several County requirements for sediment control. These included a grading plan, silt fencing limits and vehicle tracking control. Now that we have met these requirements we will begin importing dirt this coming Monday and should be on our way with our renovation work. The County will be periodically inspecting us throughout this construction project.
Friday, September 25, 2009
Soggy Start
Posted by Unknown at 7:14 AM
Labels: Driving Range, Renovation and Construction