Another hole of laterals has been completed getting us closer to being back on schedule as far as lateral installation goes.

The pulling was not as clean as the first two holes, due to heavy soil conditions found on the third hole. Additionally the soil was becoming extremely dry and caused a little heaving along the pull lines. These areas will be monitored closely, if proper settling does not occur measures will be taken to lower the disruption.