Showing posts with label Concrete. Show all posts
Showing posts with label Concrete. Show all posts

Tuesday, December 31, 2013

Pouring Concrete

It's only fitting to have a post on the last day of 2013 in a year of infrequent posting.

Today concrete was finally flowing and progress is slowly ramping up as we get past the holidays that have slowed us getting out of the ground. Footers were poured today which will now allow the forming of foundation walls to begin on Thursday. Our next pour is scheduled for this coming Monday.

Today's Action

Friday, October 16, 2009

Busy Day

Lots of activity took place today on the driving range as the project begins to hit high gear. The shaping of the features continues and is now at a fine shaping point. Moving forward, the features that are currently shaped in will now only receive minor tweaking tying them into existing grades.


Lots of activity going on

Irrigation laterals and heads continue to be installed at a pace that improves on a daily basis. To date we have installed more than 7000 feet of pipe in the last weeks time.

Today we also poured concrete in a newly enlarged parking area. The new concrete parking area will help to better accommodate multiple carts that are parked at our extremely busy driving range tee.

New forms in place
Pouring concrete





Thursday, June 4, 2009

Concrete Repair

The contractor has begun to replace the concrete that was removed or cut during the irrigation installation. We originally had the concrete work scheduled to be done by a sub- contractor and came to find out on the day they were suppose to start work they went out of business. Allot can happen in a couple of weeks in this day and age.

Repairs were made on holes #8,#9,#10 and #17 yesterday and the remaining holes will be completed over the next several day as the weather allows.



Loading Up

Finished Product

Monday, October 20, 2008

New Concrete


Today we were finally able to pour the new concrete finger on the ninth hole after scheduling delay’s caused by the weather early last week. The new path will allow for an additional exit point from the fairway, which will help spread out the traffic flows.

This path will not be used until next season due to the fact that some additional sod work will have to take place to properly tie in with the existing terrain.