Thursday, October 23, 2008

Pipe Pulling

The pulling of the laterals and wire on the first hole has begun. On this hole alone there are over 225 heads that have to be installed. This will take a crew of fifteen, three to five days to complete the installation.

Each lateral will have approximately twenty heads installed and they will become live as soon as each lateral is complete.

Below is a video of the pulling operation.