Irrigation Renovation Schedule Fall 08

In just over two weeks the irrigation system renovation will begin and there will be times disruption will occur. Below is the schedule of work to take place with a sequence of areas that will be worked on. Keep in mind this is a schedule and a job of this size has many variables, of which some can be foreseen and others not. It is critical that we stay on schedule, so that the new mainline is completely installed and laterals are installed on critical holes. If these deadlines are not met, a significant problem will occur due to the fact that new system will be operating at a lower pressure, which requires that the previously mentioned components are installed.

September 8: Hole #1 Mainline
September 15: Hole #2 Mainline, road bore to #3, ½ of 3, road bores 4 to 5 and 7 to 8
September 22: Balance Hole #3 & #4 Mainline, Complete back 9 Road Bores
September 29: Hole #5 & ½ of #6 Mainline
September 6: Balance #6 & #7 Mainline
October 13: Hole #8 & ½ of #9 Mainline start laterals #1
October 20: Balance #9 and #10 Mainline finish laterals #1
October 27: Hole #18 Mainline complete laterals #2
November 3: Holes #17 and #11 Mainline start laterals #3
November 10: Holes #12 and #13 Mainline finish laterals #4
November 17: Holes #14 and #15 Mainline start laterals #5
November 24: Hole #16 Mainline & clean-up finish laterals #5
December 2008: Install mainline on range, new booster pump & turbine conversion