Thursday, November 20, 2008

Five is Finished


We have completed the lateral installation on the fifth hole. This will be the end of the line for lateral installation for the remainder of the year. As per the contracted schedule we were planning on only doing the first five holes of laterals, with the focus being the installation of the mainline throughout the entire course.

The additional work force will now be able to focus on mainline installation, so that we can come closer to meeting our original goals. In all reality we will not hit our goal of total mainline installation this year, but with any kind of favorable weather we should get close. At this point I am projecting that we will be three holes short on mainline installation. This is not a huge problem as far as the overall work schedule because this should be easily made up next spring once works resumes.